OSHA Inspection: W & L GROUP CONSTRUCTION INC.

Programmed Related inspection · Safety discipline

On , OSHA opened a programmed Related safety inspection of W & L GROUP CONSTRUCTION INC. in 842 41ST ST., BROOKLYN, NY 11232 (NAICS 236220). OSHA activity number 336448204.

Watch W & L Group Construction INC. — free Get an email when a new federal OSHA severe-injury report for W & L Group Construction INC. is published. One employer, no account, unsubscribe in one click.
Site address
842 41ST ST.
City
BROOKLYN
State
NY
ZIP
11232
Mailing
34-28 COLLINS PLACE, FLUSHING, NY 11354
Inspection type
Programmed Related (J)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
Employees
4
Ownership type
A

4 citations on file for this inspection.

1926.350 A10

Serious Gravity 5 1 instance 4 exposed
Issued
Penalty
Initial $1600.00 · Current $1600.00
29 CFR 1926.350(a)(10): Oxygen cylinders in storage were not separated from fuel-gas cylinder or combustible materials (especially oil or grease), a minimum distance of 20 feet or by a noncombustible barrier at least 5 feet high having a fire-resistance rating of at least one-half hour.    a) 5th floor, center of building:    An oxygen cylinder was stored adjacent to an acetylene cylinder for 5 days without use. Employees who worked on site were exposed to explosion and fire hazards. On or about 09/19/12.    Note:  Because abatement of this violation is already documented in the inspection case file, the employer need not submit certification of abatement for this violation as normally required by 29 CFR 1903.19.
Recent events (1)
  • — Z (S) $1600

1926.404 B01 I

Serious Gravity 5 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1926.404(b)(1)(i): General. The employer shall use either ground fault circuit interrupters as specified in paragraph (b)(1)(ii) of this section or an assured equipment grounding conductor program as specified in paragraph (b)(1)(iii) of this section to protect employees on construction sites. These requirements are in addition to any other requirements for equipment grounding conductors.    a) 4th floor, center of building:    Employees used electric powered chop saw and screw gun to do carpentry work. The chop saw and the screw gun were connected to extension cords, which were routed to electric outlet devices on the 1st floor and were not provided with ground fault circuit interrupters. On or about 09/19/12.    NOTE:  THE EMPLOYER IS REQUIRED TO SUBMIT CERTIFICATION OF ABATEMENT FOR THIS ITEM.  FAILURE TO COMPLY MAY RESULT IN AN ADDITIONAL PENALTY OF $1,000 AS PER 29 CFR 1903.19.
Recent events (1)
  • — Z (S) $2000

1926.404 F06

Serious Gravity 5 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1926.404(f)(6): The path to ground from circuits, equipment, or enclosures was not permanent and continuous.    a) 1st floor, west side, below circuit breaker panel:    Employees used electric powered chop saw and screw gun to do carpentry work. The chop saw and the screw gun were connected to extension cords, which were routed to electric outlet devices on the 1st floor. The extension cord that was plugged into the outlet device was missing a ground pin. On or about 09/19/12.    NOTE:  THE EMPLOYER IS REQUIRED TO SUBMIT CERTIFICATION OF ABATEMENT FOR THIS ITEM.  FAILURE TO COMPLY MAY RESULT IN AN ADDITIONAL PENALTY OF $1,000 AS PER 29 CFR 1903.19.
Recent events (1)
  • — Z (S) $2000

1926.405 G02 IV

Serious Gravity 5 1 instance 4 exposed
Issued
Abate by
Penalty
Initial $2000.00 · Current $2000.00
29 CFR 1926.405(g)(2)(iv): Flexible cords were not connected to devices and fittings so that strain relief is provided to prevent pull from being directly transmitted to joints or terminal screws:    a) 1st floor, west side, below circuit breaker panel:    Employees used electric powered chop saw and screw gun to do carpentry work. The chop saw and the screw gun were connected to extension cords, which were routed to electric outlet devices on the 1st floor. The extension cord that was plugged into the outlet device was not provided strain relief. On or about 09/19/12.    NOTE:  THE EMPLOYER IS REQUIRED TO SUBMIT CERTIFICATION OF ABATEMENT FOR THIS ITEM.  FAILURE TO COMPLY MAY RESULT IN AN ADDITIONAL PENALTY OF $1,000 AS PER 29 CFR 1903.19.
Recent events (1)
  • — Z (S) $2000

View W & L GROUP CONSTRUCTION INC.'s full OSHA safety record →